Road Closures

Construction projects to improve Merriam’s roads are underway. In an effort to help motorists get around town without unexpected detours and delays, this page will provide information about road closures that could impact your travels. 

Learn more about Merriam’s current and planned construction projects. 

Road Work

I-35 Expansion
March 20 – November

The Kansas Department of Transportation (KDOT) is widening I-35 between 67th and 75th streets. 

KDOT will close the southbound I-35 on- and off-ramps at 75th St. starting March 23. Traffic should detour to Shawnee Mission Parkway. 

The northbound I-35 on-ramp at 75th St. will be closed mid-July through November, when KDOT anticipates the project will be complete.

I-35-2020-Phase-1
I-35-2020-Phase-2

Johnson Drive & Antioch
May 11 – June

WaterOne work. During Phase 1, northbound Antioch Road will not be able to turn left to go westbound on Johnson Drive, and westbound Johnson Drive will not be able to turn left to go southbound on Antioch Road. Phase 2 will allow northbound Antioch Road traffic to turn left to go westbound on Johnson.


65th St. 
April – July

Traffic will be restricted to one lane during this project. This project includes curb replacement and asphalt surfacing. 


Johnson Drive
May – October

This project includes repaving the entire roadway, new curbs and sidewalks, new streetlights, and ADA compliant ramps. There will be partial lane closures throughout the entire project, which should be completed by mid-October, weather permitting.


Mastin St.
May – August

Traffic will be restricted during this project.